[Primexd] PrimEx RC Update: Beam energy change to 11.2 GeV
Justin Stevens
jrsteven at jlab.org
Tue Mar 5 08:32:20 EST 2019
Dear Collaborators,
Yesterday Chris Keith and the target group successfully investigated the target vacuum issue and by ~noon we began filling the target with helium. Overnight we were able to collect some production data with the target full. Unfortunately, much of last night was lost due to RF issues and a klystron which needed to be replaced.
This morning we were informed that due to the continuing RF issues maintaining gradient for the current beam energy of 11.6 GeV, the accelerator and lab management have decided to lower energy to 11.2 GeV for the remainder of this run period. Therefore we will have 2 days without beam for the accelerator to commission the beam at this energy, and hope to be back to production running on Thursday.
-Justin
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mailman.jlab.org/pipermail/primexd/attachments/20190305/390352aa/attachment.html>
More information about the Primexd
mailing list