[Sbs_gems] [EXTERNAL] UV layer 4 installation schedule
Sean Jeffas
sj9ry at virginia.edu
Mon Dec 13 20:48:21 EST 2021
Hi All,
Kondo has informed me that we may possibly start running again on January
11th instead of January 17th and has asked me to provide a detailed
schedule to get UV layer 4 installed before then. So here is the list:
https://urldefense.proofpoint.com/v2/url?u=https-3A__docs.google.com_spreadsheets_d_17HB3cim5n8oyOO8oEKXg8VNUu4f-5Fp7bxwpYvNcmzU0s_edit-3Fusp-3Dsharing&d=DwIBaQ&c=CJqEzB1piLOyyvZjb8YUQw&r=IY9rjQPVeUBORHn2z0jGy7U2Cc-U0-dYM3Rqg9Kcgwk&m=GULKPuBeq4OxxgY6oIdk8FM-9LCw69hsrRiATzAQY3zYtorAnsFx8DSKa0-bHTgM&s=kEovnNJ2Thc90p0x9iTfGd39518JV_rHqvBoUL3Ov7E&e=
There are a lot of tasks, but many of them can be done in parallel, as I
have listed. To do them in parallel we will need 4 people dedicated to
this, which we already have. I have counted that we have *13 work days* until
Jan 11th, starting today. You will notice in my spreadsheet that this will
take 13 days. However I have put several "resolve issues" days which may
not actually be used, and there are 4 weekend days that could also be
(sadly) used if problems arise. So overall I am confident that this work
could be done by Jan 11th.
Best,
Sean
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mailman.jlab.org/pipermail/sbs_gems/attachments/20211213/a5cb574b/attachment.html>
More information about the Sbs_gems
mailing list