[Sns_ppu_group] Fw: PPU weekly update

Christine Fragapane chummel at jlab.org
Fri Jun 11 16:03:36 EDT 2021


FYI

________________________________
From: Ed Daly <edaly at jlab.org>
Sent: Friday, June 11, 2021 3:29 PM
To: Christine Fragapane <chummel at jlab.org>
Subject: Fw: PPU weekly update

Hi Christine,
Please pass along to the PPU team.
Thanks,
Ed

________________________________
From: Champion, Mark <championms at ornl.gov>
Sent: Friday, June 11, 2021 12:22 PM
To: PPU Staff <ppustaff at ornl.gov>
Cc: Andersen, Ken <andersenkh at ornl.gov>; Cain, Wendy <cainwa at ornl.gov>; Ed Daly <edaly at jlab.org>
Subject: [EXTERNAL] PPU weekly update


This week we received the BES charge letter for the September Independent Project Review. This enables us to appropriately focus the review presentations that are being developed and will go through dry runs in mid-July. Presentation templates are available on the project server.



JLab moved to the next phase of return-to-work this week, which will be beneficial to the ongoing PPU cavity testing and cryomodule production.



Cryomodule 11 was moved into the accelerator tunnel this week for installation in the Linac following successful plasma processing in the RF Test Facility. PPU cavity 5 was received from JLab and will be prepared for testing in the horizontal test stand in the cryomodule test bunker. PPU cavity 13 performed well in testing at JLab following additional handling that was intended to validate the cavity assembly process following helium tank installation.



A final design review for the RTBT PPS controls cabinets was conducted, and procurement of these cabinets will begin in June so they can be installed in the winter maintenance outage.



The repaired SCL circulator was returned to SNS this week and is being prepared for high power testing.

Testing of the RFQ/DTL prototype HVCM continued at the Beam Test Facility.



The RATS-II HVAC upgrade was completed, so we now have additional on-site conditioned storage.



Unfortunately, one of the pipefitters engaged in installation work in the klystron gallery was injured this week when his leg contacted a sharp edge on a pipe hanger.  The wound was relatively minor, and the worker returned to SNS after receiving medical treatment off site.  This is a reminder to maintain awareness of nearby hazards, whether carrying out your work at SNS or working on a project at home.



Thanks for your efforts.  Be safe.  Enjoy the weekend.



Mark



Mark Champion

Project Manager, Proton Power Upgrade

Neutron Sciences Directorate, Oak Ridge National Laboratory

PO Box 2008, MS 6461, Oak Ridge, TN 37831

Mobile: 865-385-8478
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mailman.jlab.org/pipermail/sns_ppu_group/attachments/20210611/67351755/attachment.html>


More information about the Sns_ppu_group mailing list