Hi All,
See the message from the PPU Project Director.
Thanks for all the good work!
-Ed
________________________________
From: Galambos, John D. <galambosjd at ornl.gov>
Sent: Friday, March 4, 2022 1:15 PM
To: PPU Staff <ppustaff at ornl.gov>
Cc: Andersen, Ken <andersenkh at ornl.gov>; Cain, Wendy <cainwa at ornl.gov>; Ed Daly <edaly at jlab.org>
Subject: [EXTERNAL] PPU weekly update


We are working to update the PPU project schedule with the modified FY23 outage sequence, with no issues identified to date. In the Superconducting RF area, we completed the work planning for shipping and receiving the first cryomodule next week from our partner JLab. Also, the second cryomodule fabrication is nearing completion and the cavity string for cryomodule 5 is being assembled. In the RF area the initial circulators are undergoing factory acceptance testing at the vendor. Also, a traffic accident occurred while returning SNS material from the modulator vendor that was used during the vendor testing. We expect to receive and inspect this material today. In the ring area, a kickoff meeting was held with the vendor fabricating the new chicane core assemblies. In the target area cryogenic catalyst material was received at ORNL, and the mercury overflow tank procurement was awarded. In the installation area, planning was done to prioritize work needed to cooldown and operate the first 2 new cryomodules scheduled for installation this summer.



Enjoy this spring like weather and have a great weekend,  jg





John Galambos

Proton Power Upgrade Project  Director

Mobile: 865-228-1531 office: 865-576-5482






-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mailman.jlab.org/pipermail/sns_ppu_group/attachments/20220304/84ffcb3b/attachment.html>


More information about the Sns_ppu_group mailing list