[Dsg-rich] Schedule RICH stiffening tool load test

Tyler Lemon tlemon at jlab.org
Tue Oct 3 09:28:29 EDT 2017


Hello Bob, 

The last email we have, unless the one you mentioned was not sent to a mailing list sent, was is from August 8, 2017 where Doug says that he will load test the stiffening tool when it gets here (emails below in blue). 

We will contact Mark Loewus for the load test. 

Best regards, 
Tyler 


From: "Mirazita Marco" <Marco.Mirazita at lnf.infn.it> 
To: "Douglas Tilles" <tilles at jlab.org> 
Cc: "dsg-rich" <dsg-rich at jlab.org> 
Sent: Wednesday, August 2, 2017 9:57:13 AM 
Subject: Re: [Dsg-rich] RICH stiffening tool - Load test - final report 

Hi Doug, 
thank you, we will let you know as soon as we have a delivery schedule 
from the company. 
Best regards, 
Marco 


Il 2017-08-02 15:38 Douglas Tilles ha scritto: 
When it gets here! I will load test it. Doug 

----- Original Message ----- 
From: "Marco Mirazita" <Marco.Mirazita at lnf.infn.it> 
To: "Bob Miller" <rmiller at jlab.org> 
Cc: "dsg-rich" <dsg-rich at jlab.org> 
Sent: Wednesday, August 2, 2017 9:33:36 AM 
Subject: Re: [Dsg-rich] RICH stiffening tool - Load test - final report 

Hi Bob, 
we are starting the procedures for the construction of the tools for 
the 
load test and one thing we have to define is the delivery deadline. 
Could you tell us possible dates for the load test, compatibly with 
your 
duties? 
Thank you, 
Marco 


-------------- next part --------------