[dsg-hallb_rich] RICH Sector 1 hw interlocks - June 2025 post work summary
Patrizia Rossi
rossi at jlab.org
Thu Jun 12 09:12:49 EDT 2025
Thank you Tyler for the detailed report
patrizia
-------------------------------------------
# Patrizia Rossi
# Jefferson Lab
# 12000 Jefferson Avenue
# Suite 5
# Newport News VA 23606 (USA)
# e-mail: rossi at jlab.org<mailto:rossi at jlab.org>
# phone: +1 (757) 269 7740
# fax: + 1 (757) 269 5800
From: dsg-hallb_rich <dsg-hallb_rich-bounces at jlab.org> on behalf of Tyler Lemon via dsg-hallb_rich <dsg-hallb_rich at jlab.org>
Date: Wednesday, June 11, 2025 at 10:05 PM
To: tlemon--- via dsg-hallb_rich <dsg-hallb_rich at jlab.org>
Subject: [dsg-hallb_rich] RICH Sector 1 hw interlocks - June 2025 post work summary
Hi,
As promised, attached is a more detailed summary of the work carried out to restore the RICH Sector 1 hardware interlocks to full functionality.
The summary is a lot of information, but since the problem/work happened over multiple days, I wanted to have the mailing list archive the information all in one message to make it easier to refer back to in the future.
Also, as mentioned in other emails, the sector 4 humidity sensors are still not working.
Priority was given to restoring S1 interlocks and there was not enough time today to complete a second cRIO swap today.
This will be fixed on the next maintenance day scheduled on next Wednesday June 18.
-Tyler
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mailman.jlab.org/pipermail/dsg-hallb_rich/attachments/20250612/f7031bdd/attachment.htm>
More information about the dsg-hallb_rich
mailing list