[PEPPo] Daily Report June 22 2012
Arne Freyberger
freyberg at jlab.org
Fri Jun 22 08:46:37 EDT 2012
*We still need shift takers this weekend, please sign up!!!*
Opportunities to contribute to the PEPPo effort are rapidly diminishing,
sign up now before you miss it!!!
(https://misportal.jlab.org/mis/apps/physics/shiftSchedule/index.cfm?experimentRunId=PEPPo)
The end game was fleshed out and agreed upon at yesterday's 3:30pm
meeting: (https://positron.jlab.org/wiki/index.php/End_Game). The
plan has production 0.1mm W target data collection up to Sunday
morning. At this time production data collection ends and a series of
systematic studies and measurements are scheduled for the next three
shifts. Sunday
Day/Swing and Monday Owl will be a very active shifts. These three
shifts will be followed by detailed Mott measurements, which will end
Wednesday morning.
Thursday and Friday are Beam studies period, and final Injector and
QWeak studies are scheduled for these last four shifts (no PEPPo
involvement required).
The most recent Swing and Owl shifts continued data collection off of
0.1mm W target at 3.2MeV/c. With about 2.5-3.0M events per shift
collected.
RC meeting today at 3:30pm in MCC.
Arne
--
Arne Freyberger
Director of Accelerator Operations
Jefferson Lab Office: (757) 269-6268
12000 Jefferson Avenue Cell: (757) 876-6289
Newport News, VA 23606 Email: freyberg at jlab.org
-------------- next part --------------
An HTML attachment was scrubbed...
URL: https://mailman.jlab.org/pipermail/peppo/attachments/20120622/5d19c2d3/attachment.html
More information about the PEPPo
mailing list